Project overview

Sub-contract works to replace 120m of damaged foul water sewer, Pugneys Park, Wakefield.

The works included installing 600 mm dia. 525 mm dia. and 450 mm dia. pipes and associated chambers within a sheet piled cofferdam, 6m deep.  Work included 10m long sheet piles, well point dewatering, Concrete piles, ground beams and pile caps.